A new US Highway 60 bridge over Pinto Creek opened to traffic Friday, Sept. 17, replacing a 72-year-old structure on the only route between Superior and the Globe-Miami area.
This item is available in full to subscribers.
To continue reading, you will need to either log in to your subscriber account, or purchase a new subscription.
If you are a current print subscriber, you can set up a free website account and connect your subscription to it by clicking here.
If you are a digital subscriber with an active, online-only subscription then you already have an account here. Just reset your password if you've not yet logged in to your account on this new site.
Otherwise, click here to view your options for subscribing.
Please log in to continue |
A new US Highway 60 bridge over Pinto Creek opened to traffic Friday, Sept. 17, replacing a 72-year-old structure on the only route between
Superior and the Globe-Miami area.
The Arizona Department of Transportation began the $22.7 million bridge replacement project 23 months ago, constructing the new bridge just feet away from traffi c that continued using the existing structure. Then on the night of Sunday, Sept. 12, work crews closed US 60 between Superior and Miami for a round-the-clock operation to realign the roadway to the new bridge.
The 695.5-foot-long bridge opened to the public shortly before noon Friday. While both bridges were designed for two lanes of traffic, the new structure also features eight-foot-wide shoulders and can handle heavier loads. The bridge is expected to handle roughly 7,200 vehicles a day.
“US 60 is a critical route for passenger vehicles and commercial traffic, including heavy loads from mines in the area,” said ADOT Southeast District Engineer Bill Harmon. “By completing this new bridge at Pinto Creek, we’re making sure the highway will remain reliable and safe for decades to come.”
While the largest milestone of the project is complete, drivers should expect periodic lane restrictions and delays in the area through the rest of 2021. Crews will work to restore the project site to its natural state over the next several months, with work beginning shortly to remove the existing bridge.
The old bridge, opened in 1949 with an estimated lifespan of 50 years, remained safe for traffic but had reached the end of its useful life. As noted on plaques at each end of the structure, the American Institute of Steel Construction bestowed an annual award of merit for 1949’s Most Beautiful Steel Bridge, Class II. Days after closing the old bridge, crews removed the plaques so they can be donated to local historical societies.
More information about the project is available at azdot.gov/PintoCreekBridge.